North End House - In Progress

Scaffolding has now been fully erected and signed off.

The roof replacement works are well underway. All Original roof coverings are now stripped, lowered and removed from site. Felt and battening is now near completion with the tiler following closely behind.

The 1st Stone survey has been agreed and now all defective areas have been cut out ready for us to carry out our repairs. Decorators are now booked in and are ready to commence within the next 2 weeks.

Further updates to follow.